| PLANNED MAINTENANCE 8 – 14 NOVEMBER 2021 |
| DATE | AREA AND LOCATION/STREET | START | COMPLETION FORECAST |
| 8 November | Rondebosch: Albion, Campground and vicinity | 09:00 | 16:00 |
| 9 November | Claremont: Scott, Crescent, Molteno and vicinity | 06:00 | 18:00 |
| 9 November | Tafelsig: Lebombo, Kilimanjaro, Magaliesberg and vicinity | 08:30 | 18:00 |
| 9 November | Bishopscourt: Finsbury, Rhodes and vicinity | 09:00 | 16:00 |
| 10 November | Tafelsig: Swartklip Pump, 12th Avenue and 11th Avenue | 06:00 | 18:00 |
| 10 November | Gordons Bay: Chapman | 08:00 | 18:00 |
| 10 November | Gordons Bay: Crinum, Oxalis, Ixia and Mountainside | 08:30 | 18:00 |
| 10 November | Royal Ascot/Milnerton: Grand National and vicinity | 08:00 | 16:00 |
| 10 November | Hout Bay: Edmondia Close, Brunia Way, Cyphia Close, Euclea Close and vicinity | 09:00 | 16:00 |
| 10 November | Newlands: Conifer Way, Cherry Street, Cherry Close, Bisset Road and portion of Upper Rose Street | 09:00 | 16:00 |
| 10 November | Melkbosstrand: Stillwater Cove, Golf Estate and vicinity | 16:00 | 17:00 |
| 11 November | Hout Bay: Earl, Alexander, Wetlands, Brighton, Empire and vicinity | 06:00 | 16:00 |
| 11 November | Beacon Valley: Tennis, Hengelaar, Biljaart and Gymkhana | 08:30 | 16:00 |
| 12 November | Strand: Buisson, Bosman, Hennings and Nieuwenhuys | 08:00 | 18:00 |
| 12 November | Constantia: Rathfelder, Warblers, Brommersvlei and vicinity | 09:00 | 16:00 |
| 14 November | Strand: Mills, Main and Aerodrome | 06:00 | 18:00 |
| 14 November | Strand: Kerk, Phil, Palm, Nico Malan and De Neyssen | 06:00 | 18:00 |